How to use your reserve fund study as a restoration schedule

Your reserve fund study is a dense report filled with critical information to help ensure your board has a successful preventive maintenance and restoration plan. Here we explain how to transform your study into an actionable restoration schedule that supports healthy reserve fund management.

Start with physical analysis data

Your physical analysis contains all the data needed to understand when common elements and assets will require repairs or replacement. Review the items on the component inventory and compare them with the anticipated lifespan and remaining useful life (RUL). You can then review the condition assessment of each element to better understand when each element is likely to require a scheduled replacement.

Use RULs to build the schedule

RULs are an excellent resource to set project timelines based on life expectancy. Separate projects into immediate work required in under a year, short- to mid-term projects expected in 2-5 years, and long-term projects between 6 and 30 years. This schedule acts as your base timeline and should remain flexible as subsequent reserve fund studies reveal changes to RULs. Additionally, assets rarely align with predicted degradation schedules. Therefore, the physical condition assessment adjustment is an essential consideration to keep schedules updated based on actual wear and tear.

Combine restoration projects

There are several ways you can pair projects together to save time and money, including:

  • Shared resources: Pipe scaffolding is a timely setup process that can eat into project budgets. By combining projects that require scaffolding, you only pay for setup and tear-down once. For example, you can recaulk window sealant during a façade replacement project.
  • Common steps: You can also complete projects more efficiently by scheduling complex steps, such as opening up brickwork, together. For example, brick repointing and rusted lintel replacement both require time-consuming brick removal and repair. Completing the repairs together allows the contractor to save money on labour costs.
  • Damage control: An effective schedule prevents damage caused by failing components that work together as part of the building envelope. By timing brick repointing and rusted lintel replacement together, you prevent progressive window leaks from causing water damage behind the newly repaired brick.

Keep in mind that updates to building codes, changing environmental concerns, and extreme weather patterns can impact project requirements. Combined projects based on shared assets or impacted by equipment upgrades or new safety measures might no longer work together as anticipated.

Confirm project necessity

Annual inspections work as part of a comprehensive predictive maintenance plan and help avoid special assessments. Localized asset assessments confirm the accuracy of projected timelines from the most recent reserve fund study. Performing inspections prior to scheduled replacements can reveal unexpected or premature failures as well as components where degradation has not progressed as predicted. As a result, some projects can be delayed or reprioritized. Your board can also compare updated material and labour costs with the initial costs outlined in the latest study to improve reserve fund planning.

By reviewing your reserve fund study’s physical analysis and using RULs to separate your timelines, you can create an actionable restoration schedule to improve reserve fund management. Strategically combining projects and including localized asset assessments will also help structure your project planning into a far more efficient process.

The experienced restoration team at WellDone Inc., a building restoration company in the GTA specializing in building improvements for multi-unit residential buildings, can provide a thorough assessment and restoration plan based on your reserve fund study. Reach out to us today.